Stage 1 - Monks Area & Infrastructure

 

Development Stages

2018

Container Huts

 

  • 3 cointainer huts
  • Infrastructure required for the current establishment and container huts
  • Site levelling/excavation

Mar 2019 – Apr 2020

Stage 1: Monks Area & Infrastructure

  • 5 Monks’ huts including one for Ajahn Brahm
  • Sangha house
  • Infrastructure for all of the buildings
  • Sewage treatment plant

Mar 2020 – present

Stage 2: Meditation Centre – Stage 2(a)

  • 24 en-suites lay retreatants
  • Construction of the kitchen and Dãna Hall,
  • Offices and general amenities,
  • Caretakers’ cottages

Future Development

Stage 3

 

Nuns Accommodation and Dhamma Hall will be the next project following the completion of Stage 2

Opening Ceremony on 10 May 2020